If you've heard talk about a "new bridge" near US 380 in McKinney, this is the project neighbors most likely mean. It is not a crossing you can drive today. On Nov. 17, 2026, McKinney City Council approved detailed design for extending Stonebridge Drive north from US 380 to Bloomdale Road, including two new multi-span bridges over Wilson Creek (City of McKinney, File 26-1099).
The project and a timeline
McKinney's Master Thoroughfare Plan calls for this stretch of Stonebridge Drive to become a four-lane greenway arterial. The first phase is more modest: two northbound lanes from US 380 to Bloomdale Road, a full rebuild of the Stonebridge intersection at US 380, and sidewalks the length of the project. At Wilson Creek, the city will design two multi-span bridges, each for three lanes, with "signature bridge aesthetics" and bridge lighting (City of McKinney, File 26-1099).
Council approved a $3,438,500 design contract with Kimley-Horn and Associates, with authority to spend up to $3.8 million if the scope changes. The city's preliminary construction estimate is $23,963,000, with additional funding expected through street general obligation bonds in fiscal years 2027 and 2028. Design is expected to take about 15 months, and construction is anticipated to begin in 2028 (City of McKinney, File 26-1099).
Council first authorized an alignment study on March 3, 2026 (City of McKinney, File 26-0169). Community Impact had described a six-lane Wilson Creek crossing, which lines up with the city's two three-lane bridges. At the Nov. 17 meeting, Engineering Director Gary Graham said construction could begin in spring 2028 and that the city has a March 2030 completion obligation under its agreement, according to Texas Local Weekly. Council Member Patrick Cloutier called it a breakthrough after about 17 years of negotiations.
What it means for drivers and commuters
The clearest benefit is a second way in and out for neighborhoods north of US 380. Graham told council that Tucker Hill currently gets all of its access from US 380. Extending Stonebridge along the subdivision's western side would create a north-south route to Bloomdale Road, once the neighborhood connects its own streets to the new road. "There is still a gap that the subdivision needs to develop to connect their existing subdivision out to the new road," Graham said, as reported by Texas Local Weekly.
City engineers also want this work finished before TxDOT advances the planned US 380 McKinney bypass, a freeway around northern McKinney. In June 2026, the city said TxDOT's ready-to-let date was tentatively June 2028 and that bypass construction was not fully funded (City of McKinney, File 26-0512). When construction starts, drivers should plan for activity at the rebuilt US 380 intersection.
What it means for homebuyers and sellers
For buyers looking at Tucker Hill, land between US 380 and Bloomdale Road, or nearby west McKinney neighborhoods such as Stonebridge Ranch just south of the highway, this is about access and long-term connectivity. It is not a reason to assume home values will rise. A second route matters for everyday trips and for having more than one way out.
The calendar still matters. Design is just getting started, construction is not expected until 2028, and the neighborhood connection still has to be built. If you are buying or selling near this corridor, it is worth asking how access works today, what construction could mean in a few years, and how the planned bypass fits into the picture.
Thinking about buying or selling near US 380 in McKinney?
I'd be glad to walk you through this corridor and what the timeline could mean for your next move. Reach out to me, KG Nair at OnDemand Realty, at realestatebykg.com or call 469-230-1409.
Facts current as of Nov. 25, 2026. Construction dates and costs come from city documents and meeting coverage and may change.